1st Weaverham Sea Scouts

scouts kayaking between two piers. The boats are colourful.

We are a friendly group and we value our links to our local community. We have four active sections, all of which are open to boys and girls:

Beavers, for ages 6-8, meet on Tuesday evenings during term-time, between 6:15 and 7:15pm

Cubs are aged between 8 and 10½, and meet on Mondays between 6:30 and 8:00pm

  • Week 11: the windows are in!

    Following installation of the ridge tiles, the main roof construction is now complete, leaving only the join between the new and the old rooflines, and the guttering and downpipes…

    Brian Avatar
  • Week 10: on with the roof!

    With the basic roof timbers now in place, four more courses of brickwork have been added to the walls to bring them up to the underside of the woodwork,…

    Brian Avatar
  • Week 9: a bit of a rollercoaster, but with a happy ending

    Another week of good weather, and by the end of Monday the major roof trusses were in place. But that evening, a neighbour – to whom we are very…

    Brian Avatar
  • Week 8: a slow start, but things have just started again!

    What with Bank Holiday Monday and further delays sorting out the roof, it’s been a disappointing week. However the roof timbers finally arrived on Friday and Conrad and his…

    Brian Avatar
  • Week 7: we’re waiting for the roof timbers ……

    Not so much to report this week. The weather has been kind and the walls – both external and internal – have been finished as far as possible. The…

    Brian Avatar
  • Week 6: Continued solid progress

    The weather has been kind again this week and we are now at the point where the entire scaffolding is up, lintels have been installed and both the brick…

    Brian Avatar
  • Week 5: A temporary setback – followed by further great progress

    Maybe we were too ambitious last week, with the weather deteriorating and strong winds on the way…… On Sunday we were dismayed to discover that the winds had blown…

    Brian Avatar
  • Week 4: Reaching for the stars!

    Despite the change in the weather this week, our builders have continued to make good progress. Early in the week, the internal block walls were up to window cill…

    Brian Avatar
  • Week 3. The Phoenix is rising……

    … and it’s continuing to go really well. This week, the low level blockwork and brickwork has been finished; the ground was prepared; then a layer of stones was…

    Brian Avatar
  • Week 2. It’s gone!

    Great progress this week with the rebuilding project. Fortunately the weather has been kind; the old building has now gone, foundations have been dug and concrete laid. Next week,…

    Brian Avatar