… and it’s continuing to go really well.
This week, the low level blockwork and brickwork has been finished;
the ground was prepared;
then a layer of stones was added;
then a layer of sand;
then a damp proof membrane;
then insulation;
then another damp proof membrane;
and finally the concrete slab was poured.
Next week: the walls!